foundation footings
Forms for the foundation.
Lydig Construction will be working on the following this week:

1) Earthwork subcontractor to continue site grading and layout of building pad
2) PUD pulling wire and setting fuse cabinet in alley
3) Continue excavation for footings
4) Form and reinforce footings for concrete

The alley will continue to be closed for construction work all week.

There will be intermittent closures on W. Cedar Street on Monday with full closure on Tuesday.  W. Cedar will be back open on Wednesday through the rest of the week.

June 9 - 13, 2014
crews build foundation footings
Crews continue work on footings for the building foundation.
Lydig Construction will be working on the following:

1) PUD will be pulling wire and setting fuse cabinet in the alley
2) Continue excavation for footings
3) Form and reinforce concrete footings
4) Form and reinforce concrete walls
5) Begin mechanical and electrical underground

The alley will be closed for construction work all week.

June 16 - 20, 2014
Foundation work continues.
Foundation work continues.
Lydig Construction will be working on the following:

1) Continue to excavate and backfill for footings
2) Form and reinforce concrete footings
3) Form and reinforce concrete walls
4) Continue mechanical and electrical underground

The alley will be closed this week for construction work.

June 23 - 27, 2014
foundation work continues
Crews continue to work on the Civic Center foundation and utilities.
Lydig Construction will work on the following this week:

1) Continue excavation and backfill for footings
2) Form and reinforce concrete footings
3) Form and reinforce concrete walls
4) Continue mechanical and electrical underground
5) Continue installation of downspout underground lines
6) PUD and CenturyLink continuing work in the alley to energize residences North of alley

The alley will be closed for construction work all week.

June 30 - July 3, 2014
foundation work continues
Foundation work continues at the Civic Center.
Lydig Construction will be working on the following:

1) Continue backfill for footings
2) Form and reinforce concrete footings
3) Form and reinforce concrete walls
4) Continue mechanical and electrical underground
5) Continue installation of downspout and underground lines
6) PUD and CenturyLink continuing work in the alley to energize residences North of the alley

The alley will be closed for the foreseeable future until bollards are installed around the new electrical transformers.