February 2015
February 2 - 6, 2015
exterior siding.jpg
Exterior metal siding is installed.
Lydig Construction will be working on the following this week:

1)  Hanging and taping drywall on the second floor
2)  Painting walls and door frames on the first floor
3)  Starting installation of acoustical ceiling guards
4)  Installation of hardi-panels, metal siding, and sheet metal work
5)  Transit parking lot asphalt paving (weather permitting)

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.

February 9 - 13, 2015
drywall installe in lobby
Crews install drywall in the Civic Center lobby.
Lydig Construction will be working on the following:

1)  Taping drywall on the second floor
2)  Painting walls and doorframes on the first and second floor
3)  Installation of acoustical ceiling grid
4)  Installation of hardi-panels, metal siding, and sheet metal
5)  Transit parking lot asphalt paving (weather permitting)

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.

February 16 - 20, 2014
casework installed
Crews begin to install the casework in the new Civic Center.
Lydig Construction will be working on the following:

1)  Taking drywall on the second floor
2)  Painting walls and doorframes on the first and second floor
3)  Installation of acoustical ceiling grid
4)  Installation of hardi-panels, metal siding, and sheet metal work
5)  Transit parking lot asphalt paving (weather permitting)
6)  Installation of casework

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.


February 23 - 27, 2015
ceiling grid in police station
Crews install the acoustical ceiling grid in the Police Station corridor in the Civic Center.
Lydig Construction will be working on the following:

1)  Taping drywall on the second floor
2)  Painting walls and door frames on first and second floor
3)  Installation of acoustical ceiling grid
4)  Installation of hardi-panels, metal siding, and sheet metal work
5)  Transit parking lot asphalt paving (weather permitting)
6)  Installation of casework
7)  Begin grading for plaza enhancement work

The alley will remain closed for the foreseeable future until bollards can be installed around the new electrical transformers.