The City of Sequim will begin work on the Infiltration Basin Facility project at the Water Reuse Demonstration Park the first week of March. The work will take place Monday through Friday between the hours of 7:00 a.m. and 4:30 p.m.
The project includes constructing an infiltration basin, a monitoring well, reclaimed water piping, and upgrades to the existing electrical system. The infiltration basin will act as an aquifer-recharge system by conveying the excess reclaimed water from the reclamation water facility. There will be some pedestrian traffic control. The project is expected to take approximately fourteen weeks to complete. The work will be done by Kamin Excavation.
Please contact Pete Tjemsland in City of Sequim Public Works Department at (360) 683-4908 or ptjemsland@sequimwa.gov with questions.